Progress’ most mature Montney development, with 50 MMCf/d of production (including Gundy volumes) flowing through an expanded 50 MMcf/d facility.
Development Status
- Vertical Test Phase completed in Q2 2009
- Horizontal Pilot Phase completed in Q3 2009
- Phase 1 Development Phase completed in Q1 2010
- Full Development Phase began in Q1 2011